If the
EXCEL Renovations Proposition is approved
by the voters on
March 1, the
Board of Education plans to use that money for the
following 12 projects.
Note:
these costs are estimates. Actual costs would be
determined by seeking bids from contractors, but in
no case can the Board of Education exceed the
$4,940,778 once it is authorized by the voters.
|
1. |
Replace
roofing on High School music and technology
wing |
$379,000 |
|
2. |
Replace
roofing on High School library & some 2nd
floor classrooms |
$460,278 |
|
3. |
Replace
roofing on Middle School locker rooms &
adjoining corridor |
$228,000 |
|
4. |
Replace
roofing on Charlton Heights cafeteria, gym &
1 classroom wing |
$648,000 |
|
5. |
Replace
roofing on Pashley B and C quads |
$351,000 |
|
6. |
Replace
roofing on Stevens gym |
$199,000 |
|
7. |
Repair Stevens
rear roof coping covers & cornice |
$45,000 |
|
8. |
Repair Stevens
front roof coping covers, cornice & top of
parapet |
$157,500 |
|
9. |
Replace the
High School pool filters to operate
correctly and much more efficiently with the
school's new (2006) heating system |
$127,000 |
|
10. |
Replace
Pashley’s antiquated steam heating system
with a much more energy-efficient hot water
system |
$1,966,000 |
|
11. |
Upgrade
Stevens electrical capacity as has been done
at other schools |
$264,000 |
|
12. |
Replace
Stevens original, now corroded galvanized
piping |
$116,000 |
|
Total |
$4,940,778 |
An important feature of projects
1 - 6 is that the Board of Education intends to purchase
30-year-waranteed roofing, which is now available,
instead of the 20-year roofing that has been used in
the past. Given the ongoing significant expense that
the district faces in keeping its 11 total acres of
roofing in good shape, school board members agreed that
30-year materials are the better investment.
The school district's architect
estimates that 30-year-warranteed materials will
cost 17% more than 20-year materials for these six
projects, but will increase the useful life of the
roofs by 50%.
|